15 Jan 2026·Ministry of Defence·Answered
AskedWhat upgrades will be made to increase the a) power and b) torque of the Perkins CV12-6A V12 diesel engine as part of the Challenger 3 programme.
ReplyAs a precursor to the conversion of Challenger 2 to Challenger 3, the Heavy Armour Automotive Improvement Programme introduced a series of upgrades to the automotive system, including bringing the Perkins CV12‑6A engine to a common build standard. Options remain available should additional power be required in the future.
15 Jan 2026·Ministry of Defence·Answered
AskedHow many operational SSN’s were at sea as of 1 January 2026.
ReplyIt is UK policy not to disclose the operational availability or deployment details of submarines, including SSNs, as doing so would, or would be likely to, prejudice the capability, effectiveness, or security of our Armed Forces.
15 Jan 2026·Ministry of Defence·Answered
AskedWhat the out-of-service date is for a) Terrier, b) Titan and c) Trojan.
ReplyThe current Out of Service Dates (OSDs) for the platforms can be found in the table below: PlatformOSDsFuchs2029Stormer2028 (extended from 2026)Terrier2043Titan2032Trojan2040 OSDs are continuously reviewed to ensure that the British Army has the capabilities it requires to deliver against Defence commitments.
15 Jan 2026·Ministry of Defence·Answered
AskedWhat the out-of-service date is for Stormer.
ReplyThe current Out of Service Dates (OSDs) for the platforms can be found in the table below: PlatformOSDsFuchs2029Stormer2028 (extended from 2026)Terrier2043Titan2032Trojan2040 OSDs are continuously reviewed to ensure that the British Army has the capabilities it requires to deliver against Defence commitments.
15 Jan 2026·Ministry of Defence·Answered
AskedWhat the out-of-service date is for Fuchs CBRN.
ReplyThe current Out of Service Dates (OSDs) for the platforms can be found in the table below: PlatformOSDsFuchs2029Stormer2028 (extended from 2026)Terrier2043Titan2032Trojan2040 OSDs are continuously reviewed to ensure that the British Army has the capabilities it requires to deliver against Defence commitments.
14 Jan 2026·Ministry of Defence·Answered
AskedWhat criteria must be met in order to achieve Full Operating Capability for Ajax.
ReplyFull Operating Capability will see the Armoured Cavalry and other Ajax users Trained, Sustainable and Ready for Deployment. It would not be appropriate to release a complete list of criteria as to do so could, or would be likely to, prejudice the capability of our Armed Forces.
14 Jan 2026·Ministry of Defence·Answered
AskedWhat criteria was met which permitted Initial Operating Capability for Ajax to be achieved on 5 November 2025.
ReplyI refer the hon. Member to the answer I gave to him to Question 104285 on 14 January 2025. https://questions-statements.parliament.uk/written-questions/detail/2026-01-08/104285
14 Jan 2026·Ministry of Defence·Answered
AskedPursuant to the answer of 14th January 2026, to answer 104283 on Ajax Vehicles: Procurement, on what dates assurances and advice regarding the safety of the platform were provided to Ministers.
ReplyI refer the hon. Member to the answer I gave to him to Question 98241 on 12 December 2025. However, I would like to reassure him that it is my intention to provide an update on the safety of Ajax and the Ministerial Review to Parliament in the near future. https://questions-statements.parliament.uk/written-questions/detail/2025-12-08/98241
14 Jan 2026·Ministry of Defence·Answered
AskedWhat were the a) names, b) dates, c) training areas used and d) exercising units equipped with Ajax of the three exercises that took place between 23rd July 2025 and Exercise Titan Storm.
ReplyThe three exercises that took place between 23 July 2025 and Exercise Titan Storm were: Exercise CYCLONE STORM between 21 July - 1 August 2025 on Salisbury Plain Training Area by The Queen’s Royal Hussars. Exercise TRADEWIND between 17 – 24 October 2025, on Salisbury Plain Training Area by The Royal Lancers. Exercise SCORION CYCLONE between 15 September – 10 October 2025 on Salisbury Plain Training Area, involving The Household Cavalry Regiment, The Royal Lancers, 26th Regiment Royal Artillery, 6 Armoured Close Support Battalion and Royal Electrical Mechanical Engineers.
14 Jan 2026·Ministry of Defence·Answered
AskedWhere were each of the (a) 23 Ajax vehicles on Exercise Titan Storm and (b) the Ajax vehicle, subsequently used to establish a baseline for noise and vibration, (i) manufactured and (ii) assembled.
ReplyThe 23 Ajax vehicles on Exercise Titan Storm and the Ajax vehicle subsequently used to establish a baseline for noise and vibration were all part of Capability Drop 3; manufactured and assembled in Merthyr Tydfil.
14 Jan 2026·Ministry of Defence·Answered
AskedBy when will he respond to Written Question 98879, submitted on 10 December 2025.
Reply170 Ajax platforms have been delivered to Field Army Units up to and including 1 December 2025. The breakdown by variant is as follows: AJAX87ARES33ATHENA25ARGUS3APOLLO13ATLAS9
14 Jan 2026·Ministry of Defence·Answered
AskedWhat Capability Drop were each of the a) 23 Ajax vehicles on Exercise Titan Storm and b) the Ajax vehicle subsequently used to establish a baseline for noise and vibration.
ReplyThe 23 Ajax vehicles on Exercise Titan Storm and the Ajax vehicle subsequently used to establish a baseline for noise and vibration were all part of Capability Drop 3; manufactured and assembled in Merthyr Tydfil.
14 Jan 2026·Ministry of Defence·Answered
AskedPursuant to the answer of 13 January 2026 to question 101527 on Armoured Fighting Vehicles: Procurement, by when he plans re-publish the 2024-25 Ministry of Defence Accounts and publish a public correction.
ReplyI will write to the hon. Member shortly with a full response and place a copy of that letter in the Library of the House.
14 Jan 2026·Ministry of Defence·Answered
AskedPursuant to the Answer of 14 January 2026 to Question 103534 on Uncrewed Systems, when is the design phase due to be completed.
ReplyThe Uncrewed Systems Centre purpose and function has been agreed for implementation. To ensure alignment with Defence Reform, work on the design, structure and outputs for Full Operating Capability will continue through 2026. Further announcements will be made in due course.
14 Jan 2026·Ministry of Defence·Answered
AskedWhat is the breakdown of the variants of the 623 Boxer vehicles which have been procured by the British Army.
ReplyRegarding the breakdown of Boxer variants, I refer the hon. Member to the answer I gave to Question 100025 which remains extant. The Mechanised Infantry Vehicle (Boxer) programme deliveries from industry are progressing in line with the current forecasted targets. To date, 19 Boxer platforms have been fielded to the British Army.
14 Jan 2026·Ministry of Defence·Answered
AskedHow many Boxer vehicles have been delivered to the British Army.
ReplyRegarding the breakdown of Boxer variants, I refer the hon. Member to the answer I gave to Question 100025 which remains extant. The Mechanised Infantry Vehicle (Boxer) programme deliveries from industry are progressing in line with the current forecasted targets. To date, 19 Boxer platforms have been fielded to the British Army.
14 Jan 2026·Ministry of Defence·Answered
AskedPursuant to the answer of 13 January 2026 to question 101527 on Armoured Fighting Vehicles: Procurement, if he will take steps to revalidate all information in the 2024-25 Ministry of Defence Accounts.
ReplyI will write to the hon. Member shortly with a full response and place a copy of that letter in the Library of the House.
14 Jan 2026·Ministry of Defence·Answered
AskedWith reference to the Ministry of Defence accounts 2024-25, what did the retirement of the Knight and Ruler Wave Class Tankers and constructive losses of £58,081,000 relate to.
ReplyA decision was announced in November 2024 to retire Knight and Ruler Wave Class Tankers, effectively mothballed by the last Government, which had not been to sea since 2017 and 2022 respectively. Their retirement reflects value for money for the taxpayer and delivering for defence, by divesting ourselves of old capabilities to make way for the future.The constructive loss of £58,081,000 relates to the write-down of the remaining value of the Knight and Ruler Wave Class Tankers and their associated capital works, spares and consumables. It has been calculated in line with Managing Public Money and Ministry of Defence accounting policies.
14 Jan 2026·Ministry of Defence·Answered
AskedWith reference to the Ministry of Defence accounts 2024-25, what did the Melorius write-off and constructive losses of £12,552,000 relate to.
ReplyInitiated to replace an in-service capability, MELORIUS was a Chemical, Biological, Radiological and Nuclear (CBRN) Medical Countermeasure project to rapidly develop and provide immediate treatment to a person exposed to a Nerve Agent.A Commercial Off The Shelf (COTS) product became available during the development stage of the project, following changes in the commercial market. Project MELORIUS was re-evaluated and a decision was made to stop further development, with funds reinvested into procuring a COTS solution. This represented the best value for money for the taxpayer, a low-risk option and significantly reduced the delivery timescales.The constructive loss of £12,552,000 was incurred during the active management of stopping project MELORIUS. It relates to the safe disposal of 110,000 medical devices, a necessary up-front purchase, and the associated costs of development and testing of the products.In delivering the best capabilities for our Armed Forces, it is vital that we continually review the market and emerging technologies for ways to enhance our current offering, to ensure that our troops have what they need to operate effectively and the ability to respond to evolving threats.
14 Jan 2026·Ministry of Defence·Answered
AskedPursuant to the answer of 13 January 2026 to question 101527 on Armoured Fighting Vehicles: Procurement, what was the project regarding the ammunition capability of the Armour Piercing Fin-Stabilised Discarding Sabot munitions.
ReplyThe Armour Piercing Fin-Stabilised Discarding Sabot munitions was one of three ammunitions proposed to be reinstated for use in the 30mm Rarden used by the Warrior Infantry Fighting Vehicle. It did not have a specific project name.